The CRP provides federal funding to projects that decrease transportation emissions, which are defined as the carbon dioxide (CO2) emissions that result from on-road, highway sources. Although the federal Infrastructure Investment and Jobs Act (IIJA) allows for a variety of projects to be funded through CRP, Caltrans’ Carbon Reduction Strategy directs Local and State CRP funds to be invested in projects that support bicycle and pedestrian, rail and transit, zero-emission vehicles and infrastructure, and conversions of existing lanes to priced managed lanes.
2023-24 Mid-Cycle CRP
The 2023/2024 Mid-Cycle CRP Guidelines describe the policies, standards, criteria, and procedures for developing, managing, and adopting Fresno COG’s CRP program. These funds are distributed through a competitive, regional bid program based on scoring criteria and evaluated by a scoring committee. Fresno COG estimates that a total of $5,494,620 will be available funding.
FINAL 2023-24 Mid-Cycle CRP Guidelines
Final 2023-24 Mid-Cycle CRP Application Packet
Programming subcommittee convenes to review scoring criteria and call information | Jan. 30, 2024 |
Guidelines, criteria, and application packet presented to TTC/PAC for approval and initiation of call-for-projects | April 25, 2024 |
Application workshop for member agencies | May 8, 2024 |
Regional Bid project submittals DUE by 12:00PM | June 4, 2024 |
CRP Scoring Committee convenes | June 27, 2024 |
COG Policy Board approves recommended projects via resolution | July 25, 2024 |
Projects programmed into 2025 FTIP | August – October 2024 |
2025 FTIP submittal to Caltrans | Fall 2024 |
Awarded Projects
2023-24 Mid-Cycle CRP Projects
2023-24 CRP
2023-24 CRP Application Packet
2023-24 CRP Final Program Guidelines
Timeline
Programming subcommittee convenes to review scoring criteria and call information | April-May 2023 |
Guidelines, criteria, and application packet presented to TTC/PAC/Board for approval and initiation of Call-For-Projects | June 2023 |
Application workshop for member agencies | July 12, 2023 |
Regional bid project submittals due | Sept. 17, 2023 |
CMAQ scoring committee convenes | December 6, 2023 |
COG Policy Board approves recommended projects via resolution | January 2024 |
Projects programed into 2023 FTIP | August – October 2024 |
2025 FTIP submittal to Caltrans | Fall 2024 |
Previously Awarded Projects